The Villa
It is June 2021. The delivery has now taken place and after that we have been busy setting up. We had already had a lot of material transported from the Netherlands to Portugal so that after delivery we could immediately start installing the beds and bedside tables in the bedrooms. In addition, the air conditioning has been installed and we have built in the microwave. Preparations have also started for installing the artificial grass in the garden. The rest of the furnishing will be started soon. And after receiving the declaration of habitability, the process for the rental permit will be started.
It is April 12th 2021 and construction is now almost complete. The painting of the outer walls has now been completed. We are also fully engaged in the preparations for the interior. Already bought the necessary items that will be shipped at the end of May. The activities that must take place immediately after completion have also been scheduled. Then the air conditioning will be installed and the artificial grass will be applied.
It’s February 3rd 2021. The position of the barbeque has been changed and has now been installed. Inside, the floor tiles have been installed, as well as the doors, frames and carpentry of the built-in cupboards. The kitchen is now being produced and is expected to be installed at the end of February.
It is the end of October 2020 now. Autumn has already started. In Portugal the weather is still very pleasant and the progress is clearly visible. The stucco inside is ready. The pump house has been bricked and the concrete floor under the pavement has now also been installed. Soon the plaster work will start outside.
It is the 29th of July 202 and we have arrived in Nadadouro and have visited the construction site. There is good progress in the construction. The walls are ready for the plasterwork and the finishing floor will be installed shortly. Soon we will post some more pictures we took this week.
It is now June 24 2020 and construction is progressing steadily. The masonry has been installed since mid-May and grooves have been milled in the walls for all pipes and cabling. We have regular contact with the contractor to discuss plans and finalize them. The plans for the kitchen and the fixed barbecue are now also with the contractor and we will discuss and finalize them shortly. In the summer holidays, despite the Corona virus, we still go to Portugal as planned a long time ago. There we will meet the buyer counselor to discuss various matters. Think of the colors of the pool, the way of heating the pool, the finish of the interior walls, floors, paving and the implementation of the toilets tiles, taps in the bathrooms. We’re looking forward to it. Lets go to the next phase !!